Client: General Authority of Civil Aviation. Contractor: SAUDI BINLADIN. Consultant: Dar Al-Handasah. Project Start Date: July 2019. Project Completion Date: January 2020. Main Works:
Aluminum Curtain Walls (SCHUCO):1000 M2
ACP Cladding (ALUCOBOND):3400 M2
Stainless Steel Cladding (Ceiling):1500M2
Spider System:3000M2
Steel Structure with Frameless Glass Partition (Boarding Bridges):5Ton / 600M2